A burn-down chart shows how much work is left over time, so the line falls toward zero. A burn-up chart shows how much work is finished and also draws the total scope, so scope changes are visible. Use a burn-down chart when scope is stable, and a burn-up chart when requirements change often.
Burn-down and burn-up charts are two of the most common visual tools for tracking progress in Agile and Scrum projects. Neither is required by the Scrum framework, yet many teams use them to see whether work is on track and to share progress with stakeholders.
They look similar and use the same axes, but they tell different stories. This guide explains what each chart shows, how to read it, how the two differ and how to choose.
What is a burn-down chart?
A burn-down chart is a graph that shows the work remaining against the time left. The vertical axis shows remaining effort, usually measured in story points for software teams or in tasks and hours in other fields. The horizontal axis shows time, usually in days.
Two lines are drawn. An ideal line slopes down evenly from the total work to zero by the end date. The actual line shows what the team has really completed, so the gap between the two shows whether the team is ahead or behind.
Benefits of a burn-down chart:
- Simple to read, which suits sprint tracking.
- Shows total unfinished work at a glance.
- Daily updates help spot problems early.
- Gives a sense of the team’s working pace.
- Helps judge whether the sprint goal is likely to be met.
- Easy to share with stakeholders.
What is a burn-up chart?
A burn-up chart shows the work completed over time, plotted against the total scope. It uses the same axes as a burn-down chart, but the completed-work line rises instead of falling.
Its key feature is the scope line. When new work is added or existing work is removed, the scope line moves up or down, so everyone can see the change. This one detail makes the burn-up chart far more transparent for projects where requirements shift.
Benefits of a burn-up chart:
- Shows work done so far, which is motivating for teams.
- Makes scope changes visible instead of hiding them.
- Helps forecast the completion date by comparing the two lines.
- Improves communication with stakeholders who want the full picture.
- Works well at both sprint and release level.
How to read each chart
Reading a burn-down chart. If the actual line sits above the ideal line, the team has more work left than planned and may be behind. If it sits below, the team is ahead. A flat stretch means little progress. A sudden upward jump usually means scope was added, but the chart does not say so directly.
Reading a burn-up chart. The completed line should climb toward the scope line. When the lines meet, the work is finished. If the scope line rises, new work was added, and the completed line must catch up with a higher target. A widening gap between the two lines is an early warning.
Burn-down vs burn-up: key differences
| Area | Burn-down chart | Burn-up chart |
|---|---|---|
| What it shows | Work remaining | Work completed and total scope |
| Line direction | Falls toward zero | Rises toward the scope line |
| Scope changes | Hidden in the remaining-work line | Shown clearly on the scope line |
| Best for | Stable scope, sprint tracking | Changing scope, release tracking |
| Simplicity | Very simple | Slightly more detail |
| Stakeholder view | Quick status | Full progress story |
| Forecasting | Compare actual line with ideal | Compare done line with scope line |
The main weakness of a burn-down chart is scope blindness. If a team finishes ten points of work and the product owner adds ten new points, the line stays flat. Observers may think the team made no progress, when in fact it delivered steadily. A burn-up chart shows both movements separately.
Which chart should you use?
Two questions usually decide it.
1. Who is the audience? Burn-down charts suit viewers who only need a quick status. Burn-up charts suit those who want to understand how the project was managed, including changes along the way.
2. How stable is the scope? If tasks and features rarely change, a burn-down chart keeps things simple. If features are added, removed or reshaped often, choose a burn-up chart.
Many teams use both: a sprint burn-down for the development team and a release burn-up for the product owner and stakeholders.
A short example (illustrative)
A team plans a release of 100 story points over 10 sprints.
After sprint 4, the team has completed 40 points. A new regulation forces the addition of 20 points, so the scope grows to 120.
- On a burn-down chart, remaining work shows 60 points at the start of sprint 5, the same as the plan implied before the change. The added scope is not visible.
- On a burn-up chart, the completed line sits at 40 and the scope line jumps from 100 to 120. The change is clear, and it is obvious why the finish date moves.
This is an invented example to show the difference. The numbers are not from a real project.
How to create either chart
Both charts can be drawn by hand on paper or built in a spreadsheet such as Excel or Google Sheets. Many project tools also generate them automatically.
Basic steps:
- Choose a unit of work, such as story points, tasks or hours.
- Set the time axis, usually days or sprints.
- Record the total scope at the start.
- Update the completed or remaining work at a regular interval, such as daily for a sprint.
- For a burn-up chart, update the scope line whenever work is added or removed.
- Review the chart with the team and discuss trends.
Keep the unit consistent. Mixing story points and hours on one chart makes it hard to read.
Burn charts and the PMP exam
Burn-down and burn-up charts are common tools in Agile and hybrid delivery, which together make up a large share of the current PMP exam. Scenario questions may ask which chart helps when scope changes frequently, or how to communicate progress to a sponsor in an adaptive project. Knowing the difference helps you choose the right answer quickly.
Check your Agile knowledge with the Free PMP Mock, and plan your preparation with the Study Plan Generator.
Common mistakes
Using a burn-down chart when scope changes often. Scope changes get hidden, and teams look slower than they are.
Updating charts rarely. A chart updated once a week loses its early-warning value.
Mixing units. Stick to one measure of work.
Using charts to judge individuals. They show team progress, not personal performance.
Ignoring the story behind the line. A flat line needs a conversation, not just a note.
Skipping stakeholder explanation. Show people how to read the chart, or they may misread a scope increase as a delay. For ideas on keeping updates short and clear, see the guide to communicating without more meetings.
Related reading
FAQs
A burn-down chart shows work remaining and falls toward zero. A burn-up chart shows work completed and total scope, so scope changes are visible.
Use it when requirements change often, or when stakeholders need to see both progress and scope changes in one view.
When scope is stable and the audience needs a simple sprint status.
No. The Scrum framework does not require them, but many teams use them as helpful visual tools.
Work, measured in story points, tasks or hours, depending on the team.
Yes. Teams often use a sprint burn-down for daily tracking and a release burn-up for overall progress.
Spreadsheets such as Excel or Google Sheets, and most Agile project tools, can create them.
More for you
SAFe in 2027: What Changed in 2026 and What to Expect Next for the Scaled Agile Framework
saketpratapsinghdm2026-11-27T21:13:07+05:30November 27th, 2026|
Critical Path Method (CPM): Steps, Float, Formulas and a Worked Example
saketpratapsinghdm2026-11-27T20:44:16+05:30November 27th, 2026|
Burn-Down vs Burn-Up Charts: Differences, Examples and When to Use Each
saketpratapsinghdm2026-11-27T20:33:17+05:30November 27th, 2026|
AI Governance in Project Management: Autonomy Levels, Stop Criteria and Stage Gates (2027)
saketpratapsinghdm2026-11-24T00:15:04+05:30November 24th, 2026|
PMO Maturity and Alignment (2027): Why You Need Both to Deliver Real Value
saketpratapsinghdm2026-11-20T14:23:47+05:30November 20th, 2026|
Risk Breakdown Structure (RBS) for AI Projects (2027): How to Map and Control AI Risk
saketpratapsinghdm2026-11-20T13:59:34+05:30November 20th, 2026|
Project Charter Guide (2026): How to Authorize Work, Align Strategy & Use AI
saketpratapsinghdm2026-11-18T00:37:14+05:30November 18th, 2026|
PMI Global Summit 2026 Highlights: 5 Major Announcements & Career Takeaways for 2027
saketpratapsinghdm2026-11-18T00:07:49+05:30November 18th, 2026|