Your project is installing Wi-Fi stations in rural areas. The response rate for the surveys sent out to residents in the affected areas has been extremely low. Expectations were to have a majority of them returned by this point in the project.
What most likely is the reason for this issue?
A. This possibility was not entered as an identified risk in the risk register.wrong
B. There was not enough budget for the Wi Fi stations
C. There is a misunderstanding of the culture of the affected stakeholderscorrect
D. The stakeholders do not have WiFi internet access.
Answer is C – Can you please xplain me how this is culture misunderstanding.