Viewing 2 reply threads
  • Author
    Posts
    • Ashish Aggarwal
      Participant
      Post count: 1

      3. You are overseeing a data center project for one of your clients. The team members have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure Dictionary. The team members also submitted their activity duration estimates to you. What should you focus on NEXT

      A. Sequence the activities using the precedence diagramming method.correct
      B. Create the activity list.
      C. Determine high-level project assumptions and constraints.
      D. Develop the project schedule.

      What is the correct answer..

    • thoufeeqahmed07
      Participant
      Post count: 1

      Option D

    • b.anupam
      Participant
      Post count: 1

      D

Viewing 2 reply threads
  • You must be logged in to reply to this topic.